Metro thru Sultan Bazaar (Hyderabad) - A failed promise. Exactly five years back (17June 2011), KCR addressing a public meeting in Sultan Bazaar warning of bloodshed if the metro dares to enter this heritage bazaar. Four years later, protesting traders pleading KCR to keep his promise (14Dec2015). Today's morning photos of metro construction - Sultan Bazaar resembles a ravaged street.
We are a group of civil society activists and researchers who are concerned about public transportation in Hyderabad. We want a mass rapid transit system that includes the buses, trains (MMTS/Metro), sidewalks and cycle paths. But the proposed elevated metro will not meet these objectives.
Showing posts with label L and T Metro. Show all posts
Showing posts with label L and T Metro. Show all posts
Friday, June 17, 2016
Saturday, February 2, 2013
Drinks, Dinner and Dance
This is just to share
on the tactics employed by the Hyderabad metro authorities (govt’s HMR and the
private L&T) to promote an image for the metro in the city. This has
nothing against the participants in the so called ‘interaction’ as we have a
lot of good friends in the journalist fraternity.
On 20th
January, the metro authorities invited many journalists for an ‘interactive’
session. It was not in their office in the city but at Taramati Baradari, a
place known for cultural shows and partying on the outskirts of the city. What
followed was less of interaction and more of drinks and dinner (with some dance
by the chiefs of the HMR and L&T metro). We are
reproducing below an item in the Times of
India, Hyderabad, 22 January 2013 under the title CHATPATA (image also inserted below the text).
“The NVS-Gadgil show “
“It was supposed to be a serious interaction (or so said the invite) with NVS Reddy and V B Gadgil over the future of metro rail in Hyderabad. But to everybody’s surprise, the event organised at Taramati Baradari over the weekend turned out to be comical with the Hyderabad Metro Rail chief deciding to entertain his guests by shaking a leg to some disco numbers being played by an orchestra team that had been especially brought in for the occasion. If that wasn’t shocking enough for the invitees, Reddy was soon heard crooning some Telugu folk songs (written to promote the metro rail) in his not-so-melodious voice leaving the gathering to wonder just what the meet was all about. The pool side party got even more colourful with the L&T CEO joining in, not to speak about the progress of the transport project, but render a peppy English number for his audience. That the duos’ show didn’t go down well with many was evident from the disgusted look on the faces of guests who were seen cursing themselves for landing up for the alleged conference. Some others, however, found solace in the delicious spread served up hot and spicy! “ (Note: NVS Reddy is the MD of HMR and V.B. Gadgil CEO and MD of L&T Metro Rail.)
“It was supposed to be a serious interaction (or so said the invite) with NVS Reddy and V B Gadgil over the future of metro rail in Hyderabad. But to everybody’s surprise, the event organised at Taramati Baradari over the weekend turned out to be comical with the Hyderabad Metro Rail chief deciding to entertain his guests by shaking a leg to some disco numbers being played by an orchestra team that had been especially brought in for the occasion. If that wasn’t shocking enough for the invitees, Reddy was soon heard crooning some Telugu folk songs (written to promote the metro rail) in his not-so-melodious voice leaving the gathering to wonder just what the meet was all about. The pool side party got even more colourful with the L&T CEO joining in, not to speak about the progress of the transport project, but render a peppy English number for his audience. That the duos’ show didn’t go down well with many was evident from the disgusted look on the faces of guests who were seen cursing themselves for landing up for the alleged conference. Some others, however, found solace in the delicious spread served up hot and spicy! “ (Note: NVS Reddy is the MD of HMR and V.B. Gadgil CEO and MD of L&T Metro Rail.)
No
wonder, one reporter was probably so much impressed with the drinks and dinner
that he likened the metro pillars with “beautiful girls playing under the
moonlight” in a Telugu daily. Now the L&T is making promotional films to
project an image for the metro. It is inviting students, executives, senior
citizens, housewives, and others to become Brand Ambassadors for Hyderabad
Metro Rail. It is ‘your chance to become a celebrity’, says half-page advts in
the local news papers in early January.
It
may be noted that the Hyd metro construction is going on in full swing in two
stretches of 8km and 12km where the roads are already very wide. The citizens
will start experiencing the traffic nightmares when the construction enters
beyond these stretches and when hundreds of shops will have to be demolished.
That will take some more time before which the authorities are trying to create
and promote graphically designed images for the metro.
Probably, more comical shows may
follow!
- Dr. C. Ramachandraiah
Monday, October 17, 2011
L&T getting jittery over Metro Rail
L&T getting jittery over Metro Rail
Co. May Ditch Project Over Land Acquisition Delay
B Krishna Prasad, Times of India, Hyderabad, 15 Oct,2011.
A very interesting and also an encouraging news to the activists the top headline item that appeared on the Times of India, Hyderabad on 15 October 2011 probably reflects the current state of affairs regarding the Hyd metro rail project, and the frustration of the L&T company in executing the same. The news item says, among other things, -
- “several reasons like delay in land acquisition and pressure by local politicians for sub-contracts, for forcing it to re-consider going ahead with the project”.
- Independent director of L&T “complained to the government over the inordinate delay in the handing over of 269 acres of land as agreed upon in the agreement”.
- “facing pressure from several local politicians to allocate subcontracts to parties of their choice”.
- “the government penalty to L&T for the delay in the project stands at nearly Rs 60 crore”.
- L&T is "paying huge interest for the loans it secured from various banks after the financial closure for the project in March 2011”.
- L&T is "annoyed with the day-today interference in the execution of the project by HMR managing director N V S Reddy”.
- L&T team has been seeking an appointment with the Chief Minister for the past one month "but has been unsuccessful so far”.
Full item is given below:
Hyderabad: Construction giant Larsen & Toubro, the private promoter of the Hyderabad Metro Rail project, has stated several reasons like delay in land acquisition and pressure by local politicians for sub-contracts, for forcing it to re-consider going ahead with the project.
Independent director of Larsen & Toubro Metro Rail (Hyderabad) Limited, a subsidiary and a special purpose vehicle of the L&T Infrastructure Development Projects, and retired IAS officer Sheila Bhide, recently complained to the government over the inordinate delay in the handing over of 269 acres of land as agreed upon in the agreement. "Apart from land acquisition, we are facing pressure from several local politicians to allocate subcontracts to parties of their choice," said sources in the company.
According to the sources, the land acquisition process is the main reason for L&T having second thoughts about the project. As per the agreement, the Hyderabad Metro Rail Project (HMR), a government body, has to acquire the land for the project and hand it over to L&T. HMR in turn has entrusted the land acquisition job to GHMC. The 71.16 km-long rail project is to be constructed on three corridors, Miyapur-LB Nagar (28.87 km), Jubilee bus Station-Falaknuma
(14.78 km) and Nagole-Shilparamam (27.51 km) at a cost of Rs 12,132 crore and L&T bagged it in global bids floated by the state government after the project was cancelled, after Maytas the original promoter went bust post the Ramalinga Raju scam.
But as of date, the land acquisition process has not made any progress in areas including the Purani Haveli Road-Shalibanda stretch in Old City, the Greenlands-Ameerpet-Madhuranagar-Krishna Nagar stretch, Country Club at Greenlands (where a station is supposed to be located), Prakash Nagar, Begumpet (parallel to the old airport flyover), from Punjagutta to Lakdi-ka-pul and Madhapur. “This is not surprisng because the project had been envisioned by Ramalinga Raju as a realtyled one. After it went phut, the government should have reviewed the project and changed the routes. But it did not do so. Everbody knew that there would be land acqusition problems,” an analyst said.
To speed up the land acquisition, the government set up a committee comprising the Greater Hyderabad Municipal Corporation (GHMC) additional commissioner (development planning) K Dhananjaya Reddy, deputy collector for land acquisition, the executive engineer of the respective corridor and the Hyderabad Metro Rail general manager for land management. But even that has not helped in speeding up the land acquisition process.
Independent director of Larsen & Toubro Metro Rail (Hyderabad) Limited, a subsidiary and a special purpose vehicle of the L&T Infrastructure Development Projects, and retired IAS officer Sheila Bhide, recently complained to the government over the inordinate delay in the handing over of 269 acres of land as agreed upon in the agreement. "Apart from land acquisition, we are facing pressure from several local politicians to allocate subcontracts to parties of their choice," said sources in the company.
According to the sources, the land acquisition process is the main reason for L&T having second thoughts about the project. As per the agreement, the Hyderabad Metro Rail Project (HMR), a government body, has to acquire the land for the project and hand it over to L&T. HMR in turn has entrusted the land acquisition job to GHMC. The 71.16 km-long rail project is to be constructed on three corridors, Miyapur-LB Nagar (28.87 km), Jubilee bus Station-Falaknuma
(14.78 km) and Nagole-Shilparamam (27.51 km) at a cost of Rs 12,132 crore and L&T bagged it in global bids floated by the state government after the project was cancelled, after Maytas the original promoter went bust post the Ramalinga Raju scam.
But as of date, the land acquisition process has not made any progress in areas including the Purani Haveli Road-Shalibanda stretch in Old City, the Greenlands-Ameerpet-Madhuranagar-Krishna Nagar stretch, Country Club at Greenlands (where a station is supposed to be located), Prakash Nagar, Begumpet (parallel to the old airport flyover), from Punjagutta to Lakdi-ka-pul and Madhapur. “This is not surprisng because the project had been envisioned by Ramalinga Raju as a realtyled one. After it went phut, the government should have reviewed the project and changed the routes. But it did not do so. Everbody knew that there would be land acqusition problems,” an analyst said.
To speed up the land acquisition, the government set up a committee comprising the Greater Hyderabad Municipal Corporation (GHMC) additional commissioner (development planning) K Dhananjaya Reddy, deputy collector for land acquisition, the executive engineer of the respective corridor and the Hyderabad Metro Rail general manager for land management. But even that has not helped in speeding up the land acquisition process.
L&T paying huge interest on loans
“We are also concerned over the delay in the land acquisition process,” B Sam Bob, principal secretary, municipal administration, told TOI.
Because of the delay in the land acquisition process, the L&T management is paying huge interest for the loans it secured from various banks after the financial closure for the project in March 2011. L&T Metro Rail (Hyderabad) Ltd has already submitted a performance guarantee of Rs 360 crore to the state government. A consortium of 10 banks led by SBI has sanctioned the entire debt requirement of Rs 11,480 crore and the equity component of around Rs 3,440 crore would be infused by the L&T group for the project.
The state should also have reasons to worry over the delay in the project, as if it does not hand over 90% of the land to the private promoter within 90 days of the payment of Performance Surety, the state would have to shell out Rs 36 lakh per day of delay in the project. The penalty clause came into effect on May 5 this year, and as of date, the government penalty to L&T for the delay in the project stands at nearly Rs 60 crore.
“Execution of the Metro Rail project is a highly skilled work and any deviation from the quality norms would doom it. Some works involving non-skilled activity can be given to local contractors, but not the major ones as is being demanded,” said the sources in the company. L&T is also reportedly annoyed with the day-today interference in the execution of the project by HMR managing director N V S Reddy.
To bring all these issues to the notice of chief minister N Kiran Kumar Reddy, an L&T team has been seeking an appointment with him for the past one month but has been unsuccessful so far. Miffed by the indifferent response, the company recently asked a senior cabinet minister to prevail over Kiran Kumar and ensure that he meets the company’s representatives. According to the minister, the CM assured him that he would meet the L&T team after the ongoing Telangana strike ends.
“We are also concerned over the delay in the land acquisition process,” B Sam Bob, principal secretary, municipal administration, told TOI.
Because of the delay in the land acquisition process, the L&T management is paying huge interest for the loans it secured from various banks after the financial closure for the project in March 2011. L&T Metro Rail (Hyderabad) Ltd has already submitted a performance guarantee of Rs 360 crore to the state government. A consortium of 10 banks led by SBI has sanctioned the entire debt requirement of Rs 11,480 crore and the equity component of around Rs 3,440 crore would be infused by the L&T group for the project.
The state should also have reasons to worry over the delay in the project, as if it does not hand over 90% of the land to the private promoter within 90 days of the payment of Performance Surety, the state would have to shell out Rs 36 lakh per day of delay in the project. The penalty clause came into effect on May 5 this year, and as of date, the government penalty to L&T for the delay in the project stands at nearly Rs 60 crore.
“Execution of the Metro Rail project is a highly skilled work and any deviation from the quality norms would doom it. Some works involving non-skilled activity can be given to local contractors, but not the major ones as is being demanded,” said the sources in the company. L&T is also reportedly annoyed with the day-today interference in the execution of the project by HMR managing director N V S Reddy.
To bring all these issues to the notice of chief minister N Kiran Kumar Reddy, an L&T team has been seeking an appointment with him for the past one month but has been unsuccessful so far. Miffed by the indifferent response, the company recently asked a senior cabinet minister to prevail over Kiran Kumar and ensure that he meets the company’s representatives. According to the minister, the CM assured him that he would meet the L&T team after the ongoing Telangana strike ends.