Showing posts with label Line-3. Show all posts
Showing posts with label Line-3. Show all posts

Friday, November 8, 2013

Lies and half-truths of Metro MDs on Land Robbery

Citizens for a Better Public Transport in Hyderabad
(A coalition of civil society organizations and individuals)
-----------------------------------------------------------------------------------------------
                                                                                 8 November 2013.
Press Release
Hyderabad Metro Rail Project
We Refute the Lies of NVS Reddy & VB Gadgil on Land Robbery
It appeared in the media today that the MDs of HMR and L&T Metro, Mr. NVS Reddy and V.B Gadgil are reported to have said that they have not taken an inch of excess land for the metro, and in fact there is still a shortfall of 22 acres or so.
We would like to reiterate that they have already taken 71 acres of excess lands which are not mentioned in the Concession Agreement. We challenge them to disclose the full details and put up the same in their websites. We are prepared for a public debate on this. This is nothing but a daylight robbery of precious public lands worth thousands of crores of rupees. We are talking about the land details listed in pages 179-80 of the Agreement and not about the lands meant for depots and maintenance at Nagole, Miyapur and Falaknuma. They are trying to hoodwink the people by covering up these issues, and only talk about the completing of the Nagole-Mettuguda stretch etc. etc.

NVS Reddy says that those who have been making allegations in the last five years have not proved anything. In fact it is the other way round. All allegations made by us have been proved. The fact that NVS Reddy refuses to appear on a common platform with us for a debate itself is a proof of our correctness in this.
1. We would like remind NVS Reddy and the public that the Order of Justice L. Narasimha Reddy of AP High Court in March 2012 justifies our position that there is no transparency in this project. We quote from the Order:
-          “The effort of the HMR appears to be, to shield or immunise itself from any plausible objections, and unfortunately the State, in its anxiety to spread a red-carpet to a private agency, has chosen to violate and break the law, enacted by itself.”
-          “there is a serious lacunae in the very launching of the project, under the A.P. Tramways Act; though it is almost a full-fledged railway.”…”it is totally impermissible to establish a ‘Railway’, in name, structure and purport, under A.P. Tramways Act.”
-          “Metro Rail was granted on earlier occasion in favour of an agency, in a similar clandestine manner, keeping the entire project away from public scrutiny.” 
-          “Acceptance of the contention of the respondents would lead to disastrous consequences. A scheme, which involves transfer of vast extents of Government land, acquisition of large number of private properties, dislocation of the road transport system for a considerable time, conferring of the largesse of a high magnitude upon a private agency, cannot take place without reference to any public opinion.”
2.  We would like to question the two MDs how they are going to provide parking and circulation for stations in those places where Osmania University refused to part with lands? How are the passengers in those areas going to benefit with the lands given at Raidurg?
3. Why should the public ask for every small information through RTI which NVS Reddy is suggesting? This itself shows the high-handed attitude of the metro MD. On one hand, they are claiming this project to be the most advanced technologically but, on the other hand, they don’t want to put the important details like Concession Agreement, DPRs, land allocations and station designs on their websites. This itself shows how dubious their claims and methods are.
4. They are only talking about the lands of Old Gandhi Hospital and at Raidurg as compensation for the OU lands. This is only a half-truth. What about the 2 acres of land of Water Board at Yousufguda, 8 acres at Erramanjil, 10.25 acres of GHMC lands/properties, 17 acres of HMDA, and small amounts of lands at a few other places. These are not part of the Agreement. If not land robbery, what else is it?
5. The MDs are claiming that the project design was finalized in the pre-bidding stage itself, hence it cannot go underground at this stage near heritage buildings. If so, we would like to question them why they are not sticking to pre-bid design and are changing the alignment of Line 2 towards Old Gandhi Hospital and extending the Line 3from Shilparamam to Raidurg? Nearly 25 acres of lands are taken at these two places only.
That means, the two MDs have no problems with pre-bid designs and are willing to make changes to grab prime lands but will not do so to protect the historic heritage precincts. If not hypocrisy and malicious intentions, what else is it?

6. We would like to appeal to Shri KCR and TRS party that if they are serious about protecting the heritage of the city, they need not wait for the metro to be completed and then demolish it. If they are sincere about their claims, they should demolish the piers NOW in front of the Public Garderns.
 If the two MDs are serious about establishing the transparency in the dealings of this project, we demand that they put up in their websites all the details regarding –
-          Concession Agreement,
-          Detailed Project Reports,
-          Lands promised in the Agreement and lands allocated along with the location and extent, 
-          Complete designs of all the metro stations along the three corridors (this project is known to have got the best design award globally but the designs for several crucial metro stations are not even ready),
-          Complete designs of the intersections of the Corridors with one another at three places.
If there is transparency and honesty in the affairs of the project there is no need to indulge in publicity gimmicks by organizing competitions in the name of “pick a click”, “Brand Ambassadors”, metro coach exhibition  etc. to hoodwink the public especially the youth and students.
We would like to advise the so-called “brand ambassadors” to read the Concession Agreement and understand it before competing in these events. Otherwise, they would be spreading only lies and become pawns in the hands of the metro authorities.
This is an externally shining project like “medi pandu” but, if opened, a lot of muck will come out.
Sd/-
Dr. C. Ramachandraiah, Social Scientist, Convenor, Citizens for Better Public Transportation
in Hyderabad (Mobile: 94400 35405).
Mr. S. Jeevan Kumar, State President, Human Rights Forum, Andhra Pradesh
Mr. B. Ramakrishna Raju, State Convenor, National Alliance of Peoples Movements (NAPM), A.P.
Mr O.M. Debara, General Secretary, Forum for a Better Hyderabad.


Wednesday, August 29, 2012

L&T Hyd Metro gets 15 acres at Raidurg - scandal unfolding too fast?


Our comment: L&T Hyd metro scandal is unfolding too fast. We have been saying from the very beginning that it is a land-real estate project in the garb of metro. 15 acres of land at Raidurg in the IT hub Gachibowli area is the key for extension of the metro route by 1 km. This was not part of the Concession Agreement. Instead of at Shilparamam the Line-3 will now terminate one kilometre away. The news item says: “The terminal station at Shilparamam was aborted since the site was found to be on a lake bed.”  What a farcical reason. If so, didn't they know it before? It also says: there would be no need to acquire "any land for parking and circulating areas for the stations from institutions like Osmania University, National Institute of Nutrition, Koti Women’s College and others.” If so, then how are you going to provide parking space for commuters at these stations?
Metro rail extended till Raidurg (The Hindu, Hyd, 29 Aug 2012)
Hyderabad Metro Rail’s Line Three from Nagole to Shilparamam will now terminate one kilometre away at Raidurg with the Government issuing orders allotting 15 acres for developing parking and circulation area for the station on Tuesday.

The land was under the possession of A.P. Industrial Infrastructure Corporation (APIIC) and has been handed over to the metro rail authorities for Rs.9 crore towards development charges excluding the land cost.

It will be part of the 269 acres to be provided for the project and apart from land for depots at Miyapur, Nagole and Falaknuma, 57 acres are for parking and circulation at the overhead stations.
With Raidurg land allotment, another 12 acres remain to be given. The terminal station at Shilparamam was aborted since the site was found to be on a lake bed.

The elevated train will now take a left turn near Hi-Tec City and culminate near the Mindspace-Raheja edifice at Raidurg, explained HMR Managing Director N.V.S. Reddy. The new station should come as a boon to the estimated 2 lakh-odd people working in the hub including those working in the adjacent financial district. It would also mean avoiding seeking any land for parking and circulating areas for the stations from institutions like Osmania University, National Institute of Nutrition, Koti Women’s College and others.

The extra kilometre for Line Three will escalate the Rs.14,132 crore project cost by Rs.200 crore. The third corridor will now be 28.52 km/24 stations. Line One is from Miyapur-L.B.Nagar – 28.87 km/27 stations and Line Two proposed from Jubilee Bus Station-Falaknuma is 14.78 km/16 stations and overall, the metro rail covers 72.16 km.

Monday, July 11, 2011

Hyderabad metro should be underground in several parts- says the DPR

Namaste Telangana, a Telugu daily formed for the cause of a separate T state, has written a series of 16 stories with the last one appearing today (11 July). For us fighting against the elevated metro in the last few years, several of the contents were familiar. What surprised us is the revelations based on DPRs (detailed project reports) which are not shared by the authorities even under RTI (my petition is pending in the State Info Comn). A few of those are given below –
-          - The DPR-2003 (prepared by DMRC of Delhi Metro, prime consultant to Hyd metro) talks of the taking most of the Line-2 underground. This is the Line in which Sultan Bazaar traders have been fighting against demolitions. But the state govt (the headed by Mr. Naidu) preferred elevated and told the DMRC that most of the roads will be widened.
-         -  It is amusing to find the name of a popular road (Sardar Patel Road) and a never-heard of road (Krishna Prasad Road) appearing in the old city on Line-2. (The ‘consultants’ who are hardly familiar with the city would have prepared these reports).
-         - The Line-3 between Secunderabad and Hitec City was not feasible as elevated corridor from engineering point of view due to steep gradients and four flyovers enroute (in parallel). It was recommended to be partly underground and partly elevated.
-          - Some pillars in Line-3 will have to go upto a height of about 100 ft.
-         -  The metro project’s managing director (MD) should be a technocrat of impeccable integrity (what we have is a railway accounts officer, whose integrity is questionable, and who got appointed in the same post till he retires!).
More later...