నిజంగా అయితే "మాట తప్పిన మెట్రో" అని కాప్షన్ వుండాలి. 
Hyd Metro Rail wants to default now. HMR entered into an MoU with Ministry of Road Transport & Highways (MORTH), GoI to build 11 flyovers parallel to the elevated metro on the 29-km corridor-1 (Miyapur-LB Nagar) on National Highway-9. It was signed on 18th October 2011. Timeline was to complete those flyovers in 4 years i.e., by October 2015. Works have not even been started. We argued then that construction of these flyovers will cause more damage the city. We even addressed a press meet. When the metro is brought in as a solution to traffic, why flyovers again? Can the existing roads provide sufficient space to build those flyovers parallel to the elevated metro corridor? Now, MORTH asked HMR to deposit Rs.300 cr to build those flyovers. HMR doesn't want to do it. The news item given below in Eenadu Telugu daily (24 July 2015) says that the HMR has changed its mind. If so, why did it sign the agreement with MORTH?